PERT is an excellent tool for estimating project deadlines when there is uncertainty. It operates as follows:
- 
Establishing Three-Time Estimates for Each Task
- 
Optimistic (O): Best-case scenario.
 
- 
Pessimistic (P): Worst-case scenario.
 
- 
Most Likely (M): Expected duration.
 
 
- 
Calculating Expected Time with the PERT Formula
TE= O+4M+P/6
This weighted formula mitigates the effects of extreme instances. 
- 
Identifying Critical Path - Once task durations have been assessed, PERT can help determine the longest path through the project.
 
- 
Assessing Variability and Risk - PERT gives a standard deviation estimate to help project managers prepare for schedule concerns.
 
PERT enhances planning accuracy by including statistical analysis, particularly in projects with unpredictable work durations.