Hey @sradha, yes there is a way by which you can do exactly what you want. This is known as dependency in testNG. 
Dependency is when you have a function which needs to run after a particular function/s completes testing. By this you can do exactly same as you require.
All you need to do is you need to make a test function dependent.
  @Test (dependsOnMethods= "h2" )
  public void h1() 
  {
  System.out.println("test case 1");
  }
  @Test
  public void h2() 
  {
  System.out.println("test case 2");
  }
  @Test
  public void h3() 
  {
  System.out.println("test case 3");
  }
  @Test
  public void h4() 
  {
  System.out.println("test case 4");
  }
This way h1 will run only when h2 is completed.